I suggest a new feature to allow cancelling scheduled downtime once it has started. The documentation states: "When an scheduled downtime is "working", it couldn't be neither modified nor deleted. "  I verified this statement is currently accurate.  There are two scenarios that this new feature is useful.

1. The scheduled downtime activities complete early. That is, instead of taking 8 hours, only 2 hours were needed.

2. The scheduled downtime is accidentally entered for a large time span. For instance, instead of for 8 hours, you enter the date resulting in 1 year and 8 hours. There is no way to end this scheduled downtime, it seems.

The consequence is no network management monitoring or editing of the selected agents is allowed/provided until the downtime ends, possibly a year later! (In my case, I accidentally set it for an extra day later.)
Logged

darode
Full Member
***

Karma: 0
Offline Offline

Posts: 45


View Profile
« Reply #1 on: January 03, 2012, 11:23:43 AM »

Hi pmcdaid,

I have added your suggestion to our roadmap and will be evaluated by our development lead.

Thanks for your feedback!
Logged

knoxel
Newbie
*

Karma: 0
Offline Offline

Posts: 8


View Profile
« Reply #2 on: February 23, 2012, 01:58:39 PM »

Well, there is a 3rd scenario... I'd like to have this feature. See the screenshot